RIS citation export for MOPB06: Installation and Commissioning of the Exactly-Constrained X-Ray Mirror Systems for Sirius/LNLS

TY  - CONF
AU  - Zilli, V.B.
AU  - Bueno, C.S.N.C.
AU  - Claudiano, G.V.
AU  - Geraldes, R.R.
AU  - Kontogiorgos, G.N.
AU  - Lena, F.R.
AU  - Luiz, S.A.L.
AU  - Moreno, G.B.Z.L.
AU  - Pinto, A.C.
AU  - Rodrigues, G.L.M.P.
AU  - Souza, M.S.
AU  - Volpe, L.M.
ED  - Jaski, Yifei
ED  - Den Hartog, Patric
ED  - Jaje, Kelly
ED  - Schaa, Volker R.W.
TI  - Installation and Commissioning of the Exactly-Constrained X-Ray Mirror Systems for Sirius/LNLS
J2  - Proc. of MEDSI2020, Chicago, IL, USA, 24-29 July 2021
CY  - Chicago, IL, USA
T2  - Mechanical Engineering Design of Synchrotron Radiation Equipment and Instrumentation
T3  - 11
LA  - english
AB  - Innovative exactly-constrained thermo-mechanical de-signs for beamline X-ray mirrors have been developed since 2017 at the 4th-generation Sirius Light Source at the Brazilian Synchrotron Light Laboratory (LNLS). Due to the specific optical layouts of the beamlines, multiple systems cover a broad range of characteristics, including: power management from a few tens of mW to tens of W, via passive room-temperature operation, water cooling or indirect cryocooling using copper braids; mirror sizes ranging from 50 mm to more than 500 mm; mirrors with single or multiple optical stripes, with and without coat-ings; and internal mechanics with one or two degrees of freedom for optimized compromise between alignment features, with sub-100-nrad resolution, and high dynamic performance, with first resonances typically above 150 Hz. Currently, nearly a dozen of these in-house mirror systems is operational or in commissioning at 5 beam-lines at Sirius: MANACÁ, CATERETÊ, CARNAÚBA, EMA and IPÊ, whereas a few more are expected by the end of 2021 with the next set of the forthcoming beam-lines. This work highlights some of the design variations and describes in detail the workflow and the lessons learned in the installation of these systems, including: modal and motion validations, as well as cleaning, as-sembling, transportation, metrology, fiducialization, alignment, baking and cooling. Finally, commissioning results are shown for dynamic and thermal stabilities, and for optical performances.
PB  - JACoW Publishing
CP  - Geneva, Switzerland
SP  - 33
EP  - 36
KW  - MMI
KW  - alignment
KW  - controls
KW  - cryogenics
KW  - optics
DA  - 2021/10
PY  - 2021
SN  - 2673-5520
SN  - 978-3-95450-229-5
DO  - doi:10.18429/JACoW-MEDSI2020-MOPB06
UR  - https://jacow.org/medsi2020/papers/mopb06.pdf
ER  -